華星東方承建的上海市崇明生活垃圾焚燒發(fā)電項目二期煙氣凈化工程于2021年10月4日通過72+24小時試運行。
The flue gas cleaning (FGC) project undertaken by Huaxing for Chongming, Shanghai waste incineration plant Phase II passed the 72 + 24 hours trial operation on October 4, 2021.
該項目設計規(guī)模日焚燒處理生活垃圾500噸。焚燒線采用1臺500t/d機械爐排爐。煙氣凈化采用爐內SNCR+旋轉噴霧半干法+碳酸氫鈉干法+活性炭噴射+袋式除塵器工藝+SGH+SCR催化脫硝的處理工藝,為我司EP工程。
The plant capacity is 500 t/d of domestic solid waste. One 500 t/d mechanical grate furnace is adopted for the incineration line. The FGC adopted the treatment process of SNCR + rotary spray semi-dry + sodium bicarbonate dry + activated carbon injection + bag filter + SGH + SCR catalytic denitration. This is an EP project of Huaxing.
華星東方在上海市的業(yè)績涵蓋包括:松江二期、崇明二期、嘉定等多個項目。
The achievements of Jiangsu Huaxing in Shanghai include Songjiang Phase II, Chongming Phase II, Jiading,etc.